Your Efficiency Number Is Probably a Lie
Ask a plant how efficiently it runs and you’ll get a confident number. Ask how that number was set, and the room goes quiet. That gap is where the money is.
The standard drifted — and nobody looked
Most operational standards got soft over the years. Each time a line couldn’t hit the mark, the mark moved — a point here, a point there — until the report looked healthy and meant nothing. Nobody wants to post 43% on the board, so the board (magically) says 85% and the floor knows better.
The losses that eat your margin usually aren’t measured at all. Whether a back-office team is turning around a service or a work center is making widgets, most shops can’t say what a good hour actually looks like — so they can’t see what they’re losing against it. The knowledge gets passed down as oral tradition, and oral tradition doesn’t survive a retirement. Ask five people to walk the whole process end to end and you’ll get five different maps. You won’t find what you aren’t looking for.
What good looks like
How much can you produce in one good hour? When everything is running well, what does that one hour make? Take that number and multiply it by the hours you actually work in a week (lights on, scheduled hours).
You know what we’re going to say next: set that next to your real net output. For most companies it’s a sobering comparison — usually we hear something like, “I wish!” For best-in-class companies the two numbers match, because they’ve worked tirelessly, for years, closing all the leaks.
From there, you’ve got a great set of 5 Whys in front of you. Where are the leaks? Here are some common ones:
- Speed loss isn’t measured. Many manufacturers measure up, down, and changeover, but not the loss from running at 75% of rated speed.
- Changeovers aren’t measured correctly. The proper definition is “last good part to the next good part — at rate.”
- Recycle or “recirc” loops. People will say the product isn’t lost — but it’s the opportunity cost of the time they aren’t measuring.
- Starts and stops aren’t captured. I vividly remember a machine in LA that started and stopped some 150 times a shift — sporadic, and completely unmeasured.
Then improve in tight loops. Narrow the scope, run rapid, structured PDCA against a 3P model, and fail fast, fail cheap — on the model, not in front of the customer. Map the current state so everyone is finally looking at the same process, then map the future state you’re driving toward.
Don’t boil the ocean. Pick one work center, measure its one good hour this week, and put that real number next to the standard. The distance between them is your project list.